October 1st: work on the roundabout started


The digging and measuring have started today in the roundabout.

The proposed schedule at this moment is: Agenda

1.-11.10. Foundation work (Lainio &Laivoranta) + setting up of electricity & lighting (the electrician Kaskenlinna has chosen)

12.10. or 15.10. Spreading the vegetal earth to plantation holes and flowerbed (Kuntec)

16.10. Silhouettes arrive (B.K.Trans)

17.-18.10. Fixation of the silhouettes (firm yet to be decided)

19.10. OR 22.10. Surface work, plantation (Kuntec), painting of silhouette edges (Alice)