The digging and measuring have
started today in the roundabout.
The proposed schedule at this moment is: Agenda
1.-11.10. Foundation work (Lainio &Laivoranta) +
setting up of electricity & lighting (the electrician Kaskenlinna has
chosen)
12.10. or 15.10. Spreading the vegetal earth to plantation
holes and flowerbed (Kuntec)
16.10.
Silhouettes arrive (B.K.Trans)
17.-18.10. Fixation of the silhouettes (firm yet to be
decided)
19.10. OR 22.10. Surface work, plantation
(Kuntec), painting of silhouette edges (Alice)